THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters., This news data comes from:http://aichuwei.com
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.

- Floods kill over 30 in Indian-controlled Kashmir, displace 150,000 in east Pakistan
- Pakistanis no reprieve from floods yet
- Firefighters arrested by US immigration officials
- Marcos confers diplomatic merit award on two ambassadors
- US church shooter 'obsessed with idea of killing children'
- House panel defers 2026 DPWH budget until agency submits changes
- Marcos to create independent commission to investigate flood control anomalies
- Marcos orders lifestyle check on all govt officials amid flood projects probe
- Comelec upholds cancelation of Duterte Youth registration
- Philippines nears universal healthcare, 80% goal achieved -- Marcos